In the end we did not finish the HVAC until this past Saturday because the plumber missed the original schedule by at least two days. Thus the electrician was delayed until this past Monday. The general contractor had scheduled a four way inspection for Monday at noon and we had been asked to be there for the inspection. As it turned out the general contractor, builder and ourselves met to review the progress and the four way was postponed until Tuesday and it was a good thing. This gave us a chance to point out that there were things that were not right. First off, the framers had not contacted us to discuss the placement of plant ledges as had been promised. Thus there we were with no plant ledges. The very day the frames had put in the walls without the plant ledges we contacted our realtor who notified the builder. Our efforts were for not. We never heard on thing from the builder. Second, we were told that we could work with the electrical contractor to determine the placement of the outlets. When we arrive on Monday the boxes were all installed and cabled. Then to top it off there were only half as many outlets as we were told that there would be. Third on the list of errors was that $250 extra drain that I had asked for was plumbed straight to the main level kitchen sink. We had paid for this extra drain to provide the option of putting a kitchenette in the basement in the future, but how that "plumber" had it done, there was no way to tie into the pipes!
With all this the general contractor was very pleasant but you could tell that he was getting a little irritated with the builder, he hadn't been told all that had been agreed upon. It appears that the builder's communications with the general contractor was as good as his communications with us. The general contractor was rightfully concerned with having to bring the sub contractors back to rework things and that was going to cost money and time. In the end we worked everything out to our satisfaction, and the general contractor and the builder had and intense discussion about how this process was suppose to work. I refer to this meeting as the boxing match which I paid a large sum of money to watch. If it were not for the fact that things worked out to our satisfaction I would believe that I had way over paid for the right to see the match.
Wednesday the insulation contractor installed insulation in the upstairs of the house. We also have the windows and exterior doors installed.
Yes! everyday we are one day closer to being able to move in.
No comments:
Post a Comment